Track material receipts, consumption and current stock on each site so project operations know what to reorder and finance can reconcile with vendor bills.

5 min read·Updated 10 Oct 2026·project-managementmaterialsstock

Each project has its own on-site store. Materials come in from vendors (received against a PO), are consumed on-site by contractors, and the running balance is visible on the Store stock view.

Open the materials catalogue

Step 1: Open Project management → Materials

The catalogue lists every material SKU with its unit (cum, kg, bags) and current price benchmark.

Screenshot pendingmaterials-and-store-01.png
Materials catalogue

Step 2: Add a material

Click Add material. Fill in Code (short, unique), Name, Unit, Default rate and Category (Cement, Steel, Aggregates, Finishing, Electrical, Plumbing).

Open a project's store

Step 1: Open Project management → Store stock

Pick the project. The view shows every material with current in-stock quantity, last received date and last consumed date.

Record a stock movement

Step 1: Open Project management → Stock movements → Add movement

Pick Movement type: - Receipt — material coming in (optionally against a PO). - Consumption — material taken out for work. - Transfer — material moved to another project. - Adjustment — physical count correction.

Step 2: Pick the material and quantity

Enter the quantity in the material's unit. For receipts, pick the vendor and PO (optional).

Step 3: Save

The project's store balance updates immediately.